First pier of Delhi-Meerut RRTS corridor completed

"The foundation work, including piling and pile caps, is in full swing between New Ashok Nagar to Kondli under package six contract and around 2 km of foundation work has already been completed out of the 9.2 km elevated corridor in Delhi," it said.